Modified asphalts

Pavement with Polymer-Modified Asphalt Mixtures

THE PROBLEM: The total project length (428 km) was divided into the following sub-sections:

  • Dv. Quilca – Dv. Arequipa (Repartición) (121.549 km)
  • Dv. Matarani – Dv. Moquegua (158.234 km)
  • Dv. Ilo – Tacna (113.310 km)
  • Tacna – La Concordia (35.520 km)

Given the traffic volume this concession would sustain, the conventional asphalt mixture proposed in the initial engineering study did not meet the performance requirements for a long-term beneficial solution. Furthermore, the solution involved placing a 4 cm asphalt layer (thin thickness). The project included sections located at long hauling distances (over 4 hours), which caused the asphalt mixture to cool down, preventing the achievement of the desired compaction densities.

THE SOLUTION: TDM proposed a high-performance solution to the client, offering long-term durability and ensuring concession performance over a longer period. The polymer-modified asphalt combined with next-generation warm mix additives resolved the compaction issues.

BENEFITS:

  • Improves asphalt mixture performance.
  • Reduces thermal susceptibility.
  • Reduces moisture-induced susceptibility.
  • Allows the asphalt mixture to be transported over long distances and for extended periods.
  • Allows maintaining a single plant location.
  • Resistance to rutting, fatigue cracking, and thermal cracking.
  • Improves adhesion with the aggregate.

Share:

OTHER RELATED CASES

Construction of the new Montalvo Bridge

Cases

THE PROBLEM: The Montalvo Bridge Consortium had to carry out the construction of the new Montalvo Bridge following the collapse...

View case

Paving at the New Jorge Chávez Airport under FAA Regulations

Cases

THE PROBLEM: The construction of the new runway at Jorge Chávez International Airport demanded the most rigorous engineering standards at...

View case

The Challenge of Rutas de Lima on the Panamericana Sur

Cases

THE PROBLEM: The Rutas de Lima concessionaire needed to carry out a functional intervention on high-traffic sections of the Panamericana...

View case
¿Necesitas ayuda?